Table of Contents for Preliminary Project Plan (pE1)
Introduction
1.1 Purpose of the document
1.2 Validity of the document
1.3 Definitions of terms and abbreviations
1.4 Relationship with other documents
Project goal
Project organization
3.1 Client
3.2 Project manager
3.3 QA manager
3.4 Project organization
Framework for effort
Personnel requirements framework
5.1 Qualification
5.2 Histogram of manpower
Framework for deadlines
6.1 Start of project
6.2 Duration of project
6.3 Completion / delivery dates
Constraints
7.1 Project type
7.2 Processing
Risks
8.1 Technical risks
8.2 Quality risks
8.3 Project execution risks
8.4 External risks
Siemens AG Österreich, Program and Systems Engineering PSE
Contact:
stdSEM Webmaster
Last modified: 08/27/98 15:41
Copyright © Siemens AG Österreich 1997. All rights reserved.