Table of Contents for Preliminary Project Plan (pE1)

  1. Introduction
    1.1 Purpose of the document
    1.2 Validity of the document
    1.3 Definitions of terms and abbreviations
    1.4 Relationship with other documents
  2. Project goal
  3. Project organization
    3.1 Client
    3.2 Project manager
    3.3 QA manager
    3.4 Project organization
  4. Framework for effort
  5. Personnel requirements framework
    5.1 Qualification
    5.2 Histogram of manpower
  6. Framework for deadlines
    6.1 Start of project
    6.2 Duration of project
    6.3 Completion / delivery dates
  7. Constraints
    7.1 Project type
    7.2 Processing
  8. Risks
    8.1 Technical risks
    8.2 Quality risks
    8.3 Project execution risks
    8.4 External risks

Siemens AG Österreich, Program and Systems Engineering PSE
Contact: stdSEM Webmaster
Last modified: 08/27/98 15:41
Copyright © Siemens AG Österreich 1997. All rights reserved.